Construction Update
- Hover above the map to learn about construction plans for that area.
- Click on the map to read more about the construction process.
Three Week Schedule
[Updated September 2, 2010]
| Location |
Activity |
Date |
| Lake Corp Marina / McVey Trestle Dock | Boat removal operation by Lake Corp, daily from 6:30 a.m. to 8:00 p.m. | August - Labor Day Weekend |
| Lakewood Bay / Headlee Walkway | Staging for bypass pumps and installation of pipe liner (CIPP) | August - October 2010 |
| Main Lake | Drawdown | Labor Day - May 2011 |
| Hunt Club |
Installation of debris sump (one-lane closure, watch for flaggers) |
Mid - September |
| Alder Point |
Build lake access ramp for construction vehicles | September 2010 |
| Allen Road | coming soon | |
| Maple Circle Easement |
Remove seawall | October 2010 |
| Iron Mountain Site |
Staging area | July 2010 - May 2011 |
| Bryant Road Pump Station | Construction underway | May 2010 - February 2011 |
| Bryant Road |
Debris sump Installation involves 2-week road closure |
October 2010 - November 2010 |
| Lake Corp dredging access involves 1-lane closure | September 2010 - October 2010 | |
| Oak St. (near intersection of Oak and Palisades Terrace Dr.) |
Installation of debris sump | September 2010 |
| Oswego Pointe Apartments |
Pipe liner (CIPP) installation and bypass pumping | August 2010 - October 2010 |
| Foothills Road |
Install manholes and pipe in road | August 2010 - October 2010 |
| Dates are tentative and may change. Some represent a range of days in which a particular activity may occur. Check back regularly for current information. The LOIS Team is committed to providing you with the most accurate information available. |